Facilities request intake
Illustrative decision brief · Fictional AI-assisted summary and queue suggestion
Should the sponsor authorize a live, human-reviewed pilot of AI-assisted request summaries and queue suggestions?
Recommendation
Hold the live pilot. Authorize a controlled redesign and offline retest. One urgent request was incorrectly routed after human review in the invented assessment; that failure cannot be averaged away by routine-case performance.
Accountability
The fictional sponsor owns the advance decision. Facilities operations owns final assignment and the baseline; security approves the test data; technology must accept monitoring, incident response, and support before handoff.
Options considered
What the fictional test found
- Of 120 closed requests reviewed, 96 were cleared for offline use; 24 with restricted details were excluded.
- In a 30-case timed exercise, median coordinator time fell from 6.5 to 6.0 minutes, including checking and edits. That does not yet establish net value.
- Twelve of 96 suggested queues were wrong. Reviewers missed two, including one urgent request suggested for routine handling.
- Required facts were missing in 18 drafts, and no technology team had accepted support duties.
Conditions for the next gate
- Security approves at least 100 representative cases, including urgent, multi-trade, and incomplete work, or narrows the proposed scope to the evidence available.
- Facilities and technology test source-linked fields, the urgent-case check, correction path, manual fallback, and support route.
- No urgent downgrade passes human review in the agreed set; the proposed two-minute net saving per request is tested without more reroutes and compared with recurring costs.
- The sponsor records an advance, redesign, or stop decision with named owners and a review point.